Move settings
Move settings is a TSI where you can make various settings for the Moves TSI in Planon ProCenter and the Move request wizard in Planon Self-Service.
This section describes the various settings available in the Move settings TSI.
General move settings: settings related to the Moves TSI can be made on the General tab of the Move settings TSI. These settings include:
• Activation of automatic status transitions to (user-defined) move request statuses.
• Synchronization of move lines.
If no statuses are selected in the Automatic status transition to user-defined Planned statuses and Automatic status transition to user-defined Executed statuses sections, there will be no automatic status transitions for move requests.
To set automatic status transitions for move requests
Use the following procedure to set automatic status transitions for move requests to a Planned user-defined status.
1. Go to Move settings > General tab.
2. Under the Automatic status transition to user-defined Planned statuses section, open the Move settings - User-defined 'Planned statuses' pop-up.
The User-defined 'Planned statuses' dialog box is displayed.
3. In the Available section, select the 'Planned' user-defined statuses to be assigned to move requests whose move lines have all been assigned to a move order.
4. Click the right arrow button to transfer these statuses to the In use section.
5. Click OK.
6. Click Save.
You have now made status transition settings for move requests whose move lines have all been assigned to a move order.
Setting automatic status transitions for move requests
Use the following procedure to set automatic status transitions for move requests to a user-defined Executed status:
1. Go to Move settings > General tab.
2. Under the Automatic status transition to user-defined Executed statuses section, open the Move settings - User-defined 'Executed statuses' pop-up.
The User-defined 'Executed statuses' dialog box is displayed.
3. In the Available section, select the 'Executed' user-defined statuses to be assigned to move requests whose move lines have all been completed.
4. Click the right arrow button to transfer these statuses to the In use section.
5. Click OK.
6. Click Save.
You have now made status transition settings for move requests whose move lines have all been completed.