Define calendars
Discuss with the customer if there are different calendars required that hold different:
The Building administrator can create the list manually or via available SDI import sheets.
Working days
Different start time & end time (e.g. opening hours of the building)
Special dates (e.g. public holidays per country)
Deviating hours (e.g. On weekdays opening hours are different than on Saturday)
Based on discussions with customers, Calendars can be created manually.
The Company Calendar is used for the dashboards. It depends on the setting of the Company Calendar, linked to the building, for which hours in a working day the values are displayed in the Dashboard. For example, from 09.00 till 18:00 on Monday up to Friday. For a 24/7 company/building the working hours need to be set as:
General start time: 00:00
General end time: 23:59
All days are a working day.
See the following sample Company calendar and result:
Calendars
Temperature trend